🚨 UPDATED SCHEDULE 09/10: Border Dam Entry Ramp Concrete Pours! 🚣♂️🛠️
Please note another schedule change for the border dam put-in! Concrete deliveries have been locked in, and the pour is now split across two separate days: Friday, Sept 11th, and Monday, Sept 14th.
We need hands on deck for both days to get this ramp completed!
QUICK DETAILS:
🗓️ Concrete Pour #1: Friday, Sept 11th (NEW TIME) • Meet: 9:00 AM at Carpenters Park • Bring/Wear: Work clothes, work gloves, and rubber boots (if you have them)
🗓️ Concrete Pour #2: Monday, Sept 14th (NEW DATE) • Meet: 10:00 AM at Carpenters Park • Bring/Wear: Work clothes, work gloves, and rubber boots (if you have them)
🥪 Perks: Lunch and water provided!
📞 To RSVP or ask questions: Please call Scott Rugh at 814-279-9212 if you can help out either day!